BCFC

Ashton Gate Football Stadium

Project Location: Ashton Gate, Bristol

Project Contractor: McLaughlin & Harvey

Project Value (C&I): £995k

Project Duration: 60 weeks (January 2016 – March 2017)

Project Scope: New West Stand built to the existing Ashton Gate Stadium home to Bristol City Football Club. Facilities included new Hospitality Areas, New Changing Room facilities for Home and Away visiting teams, including Executive Boxes, Offices, Admin, Kitchen and Bar facilities for the public. Work included feature MF Coffered Ceilings, Grid and Tile Ceilings, Acoustic and Fire Rated Metal Stud Partition Walls, Feature Raft Ceilings to the Executive Boxes all completed with a Tape and Joint finish.

jmp_bcfc_new_training_ground_jan21_rt0187

Bristol City Football Club Training Facilities

Project Location: Failand, Bristol

Project Contractor: Beard Construction

Project Value (C&I): £750k

Project Duration: 42 weeks (May 2020 – February 2021)

Project Scope: Brand new state of the art training facilities for Bristol City Football Club to bring the First Team and Academy Teams together. Works include a floodlit showcase pitch along with two further pitches. The building also includes a Gym, Changing Rooms, Medical and Rehabilitation Facilities and Office Spaces as well as Education and Welfare Facilities. Works included Metsec SFS installation to the external elevation, forming new Internal Metal Stud Partitions, Suspended Grid and Tile Ceilings, MF Ceilings and Acoustic Baffles with a plaster finish throughout.

Exterior General View as Bristol Bears start to use their new almost completed Training centre - Rogan/JMP - 08/07/2020 - RUGBY UNION - Beggar Bush Lane - Bristol, England.

Bristol Bears Rugby Training Facilities

Project Location: Failand, Bristol

Project Contractor: Beard Construction

Project Value (C&I): £220k

Project Duration: 30 weeks (November 2019 – June 2020)

Project Scope: Brand new state of the art training facilities for Bristol Bears Rugby, which included two full size training pitches and a covered indoor training pitch, Gymnasium, Medical Facilities, Hydrotherapy Room, Nutrition Room, Admin Offices and Player’s Lounge. Works included forming new Internal Metal Stud Partitions, Suspended Grid and Tile Ceilings, MF Ceilings and Acoustic Baffles with a plaster finish throughout.

locklease

Lockleaze Sports Centre

Project Location: Lockleaze, Bristol

Project Contractor: Jones Building Group

Project Value (C&I): £140k

Project Duration: 30 weeks (May 2017 – December 2017)

Project Scope: New Sports Centre for local community, delivering affordable first -class sports, education, and health improvements to the local community. We install Internal Metal Stud Partitions, MF Feature Ceilings to the Changing Room Area, Grid and Tile Ceilings to Hospitality, Kitchen and Bar areas

Screenshot 2025-10-30 at 08.10.02

Hangar 16U

Project Location: Brabazon, Bristol

Project Contractor: YTL Developments

Project Value (C&I): £300k

Project Duration: 30 weeks (January 2025 – July 2025)

Project Scope: Working with YTL Developments to form a new, local social hub in an historic listed 1915 aircraft hangar at Brabazon, Bristol. C&I Southwest were employed to complete new Metal Stud Partitioning, Wall Linings, Column and Beam Encasements including Suspended Ceilings and Acoustic Wall and Ceiling panels

Screenshot 2025-10-30 at 08.12.27

Entertainment Centre, Minehead

Project Location: Minehead, Somerset

Project Contractor: DR Jones

Project Value (C&I): £150k

Project Duration: 17 weeks (January 2024 – April 2024)

Project Scope: Refurbishment of the Main Centre Stage at Butlins, Minehead. C&I Southwest were contracted to install new back of house Partitioning and Wall Linings along with installing a mixture of 3000m2 of new 600 x 600 Black and White Suspended Ceilings throughout.

Screenshot 2025-10-30 at 08.12.51

St. Bernadettes Rugby Club

Project Location: Hartcliffe, Bristol

Project Contractor: Stepnell Construction

Project Value (C&I): £58k

Project Duration: 16 weeks (December 2023 – April 2024)

Project Scope: Working with Stepnell Construction to provide a new first-class sports facility for the local community in Hartcliffe, Bristol. Our works including Drylining of plasterboard to blockwork including a 3mm skim finish along with a mixture of 600 x 600 Grid and Tile Suspended Ceilings and Metal Frame standard and acoustic plasterboard ceilings to communal areas.