Case Study 1

Project Name: Chiswick High School

Project Location: Chiswick, West London

Project Contractor: JJ Rhatigan Construction

Project Value (C&I): £200k

Project Duration: 26 weeks (March 2017 – September 2017)

Project Scope: Construction of a new build two-storey Classroom block and an extension to the existing Dining Hall and an outdoor designated Dining Space, providing students with new state of the art IT and Workshop facilitites for Food Studies, Textiles and Product Design Space. Works Included forming new Internal Partitions, Suspended Grid and Tile Ceiling and a Plaster finish throughout.

Case Study 2

Project Name: Paul Kent Hall, Oxford Brookes University

Project Location: Cowley, Oxford

Project Contractor: Stepnell Construction

Project Value (C&I): £475k

Project Duration: 52 weeks (March 2020 – March 2021)

Project Scope: Refurbishment of existing resident halls for Oxford Brookes University. Works consisted of forming new Partitions, Wall Linings, MF and Metal Pan ceilings, Plastering and Acoustic Baffles

Case Study 3

Project Name: Stowe School

Project Location: Stowe, Buckinghamshire

Project Contractor: Stepnell Construction

Project Value (C&I): £375k

Project Duration: 44 weeks (December 2017 – October 2018)

Project Scope: New three and four storey building to provide study bedrooms for 60 pupils along with Living Facilities, Common Rooms and a Terrace and Gardens as well as apartments for the Housemaster and two under Housemasters. Our scope of works SFS, Cement board, Insulation and Vapour Control layer to the exterior of the building and internal Partitioning, Suspended Ceilings and Plastering throughout

Case Study 4

Project Name: Tring Park School for Performing Arts

Project Location: Tring

Project Contractor: Stepnell Construction

Project Value (C&I): £300k

Project Duration: 40 weeks (June 2018 – March 2019)

Project Scope: New Boarding House to form part of Tring Park School, which consists of 70 Student Bedrooms with En-Suite facilities, Teaching Spaces, Common Rooms, Kitchen Facilities and Theatre Workshops. Our works consisted of SFS, Cement Board, Insulation, Vapour Barrier to the external elevation and internally, Drylining to blockwork walls, Internal Metal Stud Partitions, Suspended and Acoustic Ceilings, with a plaster finish throughout

Get a free quote on any of our services.