BCFC

Ashton Gate Football Stadium

Project Location: Ashton Gate, Bristol

Project Contractor: McLaughlin & Harvey

Project Value (C&I): £995k

Project Duration: 60 weeks (January 2016 – March 2017)

Project Scope: New West Stand built to the existing Ashton Gate Stadium home to Bristol City Football Club. Facilities included new Hospitality Areas, New Changing Room facilities for Home and Away visiting teams, including Executive Boxes, Offices, Admin, Kitchen and Bar facilities for the public. Work included feature MF Coffered Ceilings, Grid and Tile Ceilings, Acoustic and Fire Rated Metal Stud Partition Walls, Feature Raft Ceilings to the Executive Boxes all completed with a Tape and Joint finish.

jmp_bcfc_new_training_ground_jan21_rt0187

Bristol City Football Club Training Facilities

Project Location: Failand, Bristol

Project Contractor: Beard Construction

Project Value (C&I): £750k

Project Duration: 42 weeks (May 2020 – February 2021)

Project Scope: Brand new state of the art training facilities for Bristol City Football Club to bring the First Team and Academy Teams together. Works include a floodlit showcase pitch along with two further pitches. The building also includes a Gym, Changing Rooms, Medical and Rehabilitation Facilities and Office Spaces as well as Education and Welfare Facilities. Works included Metsec SFS installation to the external elevation, forming new Internal Metal Stud Partitions, Suspended Grid and Tile Ceilings, MF Ceilings and Acoustic Baffles with a plaster finish throughout.

Exterior General View as Bristol Bears start to use their new almost completed Training centre - Rogan/JMP - 08/07/2020 - RUGBY UNION - Beggar Bush Lane - Bristol, England.

Bristol Bears Rugby Training Facilities

Project Location: Failand, Bristol

Project Contractor: Beard Construction

Project Value (C&I): £220k

Project Duration: 30 weeks (November 2019 – June 2020)

Project Scope: Brand new state of the art training facilities for Bristol Bears Rugby, which included two full size training pitches and a covered indoor training pitch, Gymnasium, Medical Facilities, Hydrotherapy Room, Nutrition Room, Admin Offices and Player’s Lounge. Works included forming new Internal Metal Stud Partitions, Suspended Grid and Tile Ceilings, MF Ceilings and Acoustic Baffles with a plaster finish throughout.

locklease

Lockleaze Sports Centre

Project Location: Lockleaze, Bristol

Project Contractor: Jones Building Group

Project Value (C&I): £140k

Project Duration: 30 weeks (May 2017 – December 2017)

Project Scope: New Sports Centre for local community, delivering affordable first -class sports, education, and health improvements to the local community. We install Internal Metal Stud Partitions, MF Feature Ceilings to the Changing Room Area, Grid and Tile Ceilings to Hospitality, Kitchen and Bar areas