o1

Porsche Showroom

Project Location: Newport, South Wales

Project Contractor: Beard Construction Ltd

Project Value (C&I): £650k

Project Duration: 25 weeks (Aug 2023 –

Project Scope: Working with Beard to form a New Porsche Showroom, our works consist of Internal Metal Stud Wall Linings and Internal Metal Stud Partitions, Metal Pan ceilings, MF Ceilings, feature Bulkheads with a Tape and Joint Finish throughout.

o2

Portwall Square

Project Location: Bristol

Project Contractor: Skanska

Project Value (C&I): £550k

Project Duration: August 2021 – July 2022

Project Scope: New build office block formed in central Bristol. Our works consisted of forming Insulated Wall Linings to open office areas, Internal Metal Stud Partitions and Metal Pan Suspended Ceilings to core facilities running up through the building including a tape and joint finish throughout.

o3

Imperial Tobacco

Project Location: Bristol

Project Contractor: CBRE

Project Value (C&I): £210k

Project Duration: March 2023 – August 2023

Project Scope: Reconfiguration of existing offices, forming new Internal Partitions, Wall Linings along with Suspended Grid and Tile Ceilings to newly formed offices.

o4

CVT Vets

Project Location: Portsmouth

Project Contractor: Lancer Scott

Project Value (C&I): £130k

Project Duration: March 2023 – June 2023

Project Scope: Conversion of a former building into a new Veterinary Surgery. Works consisted of forming new Internal Metal Stud Partitions, Wall Linings, MF Ceilings including Grid and Tile Suspended Ceiling, including a Tape and Joint Finish